This project progresses the success of the Electrical Generator Test Phase I project which was a desktop study to analyze a proprietary database of destruction technologies for possible advancement to field stage.  In total, 24 technologies were considered under specific operating conditions of available power source, pressure, rate, gas flow variability and composition.  In the Electrical Generator Test Phase II project, 6 technologies were derived from the original suite of projects and deployed at ATCO’s Peigan Field Station.  Each technology was analyzed independently and test conclusions were drawn to establish a check-list of sorts of optimum operating applicability of each technology.  The project conclusions have been fully reported and form the basis of an Electrical Generator Test Phase III project concept designed to deploy 3 select technologies at producer oil and gas sites.